Channel Construction on Jalan Lewa Pekayon Completed
access_time December 15 2023 02:06 PM remove_red_eye 734
Reported by Nurito | Translated by Nugroho Adibrata
Reported by Nurito | Translated by Nugroho Adibrata
The construction of the 489-meter-long water channel on Jalan Lewa RW 10 Pekayon Urban Village, Pasarebo, East Jakarta, finally completed in mid-November 2023.
It's finished but still in the finishing stage
East Jakarta Water Resources (SDA) Sub-agency's Development Division Head, Tengku Saugi Zikri said the channel built on a densely populated area was aimed to overcome flooding problem.
"It's finished but still in the finishing stage," he expressed, Friday (12/15).
Seven Infiltration Wells Built in Residential Areas on Tidung IslandThere were several points that had to be paved with hotmix, returned to their original position, especially at crossings, thus motorists or local residents would feel safe and comfortable.
Hre explained construction at this location is part of the seventh stage. This channel uses a U-Ditch measuring 60 centimeters, 40 centimeters and a 60-centimeter box culvert.
"The work takes 26 days, starting in mid-November," he concluded.